Bronx, Sequoia numbers of 10/20/05, replacement factor of 5

 

 

Formula for PBOS:

    One OpScan and one Ballot-marker replace 5 levers

    plus one Privacy booth replaces one lever

    1-5 levers   -> 1 OpScan,  1 B-marker,    1-5 P-booths

    6-10 levers  -> 2 OpScans, 2 B-markers,  6-10 P-booths

    11-15 levers -> 3 OpScans, 3 B-markers, 11-15 P-booths, etc.

    Purchase prices: OpScan $5000,  B-marker $7500,  P-Booth $200

 

Formula for DREs: One DRE replaces one lever. Purchase price: DRE $8000.

 

 

22 poll sites have 1 lever

1 OS, 1 BM, 1 PB      one site    $12,700, 22 sites   $279,400

or 1 DRE             one site     $8,000, 22 sites   $176,000

 

21 poll sites have 2 levers

1 OS, 1 BM, 2 PBs     one site    $12,900, 21 sites   $270,900

or 2 DREs             one site    $16,000, 21 sites   $336,000

 

31 poll sites have 3 levers

1 OS, 1 BM, 3 PBs     one site    $13,100, 31 sites   $406,100

or 3 DREs             one site    $24,000, 31 sites   $744,000

 

33 poll sites have 4 levers

1 OS, 1 BM, 4 PBs     one site    $13,300, 33 sites   $438,900

or 4 DREs             one site    $32,000, 33 sites $1,056,000

 

21 poll sites have 5 levers

1 OS, 1 BM, 5 PBs     one site    $13,500, 21 sites   $283,500

or 5 DREs             one site    $40,000, 21 sites   $840,000

 

14 poll sites have 6 levers

2 OSs, 2 BMs, 6 PBs  one site    $26,200, 14 sites   $366,800

or 6 DREs             one site    $48,000, 14 sites   $672,000

 

20 poll sites have 7 levers

2 OSs, 2 BMs, 7 PBs  one site    $26,400, 20 sites   $528,000

or 7 DREs             one site    $56,000, 20 sites $1,120,000

 

14 poll sites have 8 levers

2 OSs, 2 BMs, 8 PBs  one site    $26,600, 14 sites   $372,400

or 8 DREs             one site    $64,000, 14 sites   $896,000

 

8 poll sites have 9 levers

2 OSs, 2 BMs, 9 PBs  one site    $26,800,  8 sites   $214,400

or 9 DREs             one site    $72,000,  8 sites   $576,000

 

14 poll sites have 10 levers

2 OSs, 2 BMs, 10 PBs  one site    $27,000, 14 sites   $378,000

or 10 DREs            one site    $80,000, 14 sites $1,120,000

5 poll sites have 11 levers

3 OSs, 3 BMs, 11 PBs  one site    $39,700,  5 sites   $198,500

or 11 DREs            one site    $88,000,  5 sites   $440,000

 

4 poll sites have 12 levers

3 OSs, 3 BMs, 12 PBs  one site    $39,900,  4 sites   $159,600

or 12 DREs            one site    $96,000,  4 sites   $384,000

 

3 poll sites have 13 levers

3 OSs, 3 BMs, 13 PBs  one site    $40,100,  3 sites   $120,300

or 13 DREs            one site   $104,000,  3 sites   $312,000

 

1 poll site has 15 levers

3 OSs, 3 BMs, 15 PBs  one site    $40,500,  1 sites    $40,500

or 15 DREs            one site   $120,000,  1 sites   $120,000

 

3 poll sites have 16 levers

4 OSs, 4 BMs, 16 PBs  one site    $53,200,  3 sites   $159,600

or 16 DREs            one site   $128,000,  3 sites   $384,000

 

 

total number of poll sites: 214, total number of levers: 1147

 

total cost of replacement:

PBOS:    $4,216,900

DREs:    $9,176,000